Warning: Declaration of Suffusion_MM_Walker::start_el(&$output, $item, $depth, $args) should be compatible with Walker_Nav_Menu::start_el(&$output, $data_object, $depth = 0, $args = NULL, $current_object_id = 0) in /home/thetrew3/public_html/paulw/wp-content/themes/suffusion/library/suffusion-walkers.php on line 17

Land trust group aims to halt state proceedings on Berkshire Gas request to proposed pipeline

 

By RICHIE DAVIS
Recorder Staff
Wednesday, June 17, 2015

An anti-pipeline environmental coalition is calling on the Supreme Judicial Court to halt state proceedings on a request by Berkshire Gas Co. to tap into Tennessee Gas Pipeline Co.’s proposed Northeast Energy Direct project — concerned the state Department of Public Utilities is ignoring its appeal to intervene in the bureaucratic process.

With DPU’s legal hearings scheduled for June 24, 25 and 26 in Boston on Berkshire Gas’s proposed 20-year agreement to buy gas from the pipeline that would cut across 62 miles in Massachusetts including eight Franklin County towns, Northeast Energy Solutions (NEES) filed an “expedited petition” for a single judge to freeze further action in the matter.

NEES, representing Franklin Land Trust, a 130-member statewide land-trust alliance that includes Mount Grace Land Trust, as well as other conservation groups and legislative and municipal members, is one of two broad intervention petitions rejected by a DPU hearing officer on May 29.

Both were granted “limited intervenor” status, meaning they can’t require legal depositions to seek documents, testimony and other undisclosed evidence from Berkshire Gas.

Appeals were immediately filed by NEES and a coalition led by Pipeline Awareness Network for the Northeast (PLAN-NE), state Rep. Stephen Kulik, the Town of Montague and Greenfield Town Council. Ashfield and Conway also agreed to join the PLAN-NE intervention, and Rep. Paul Mark, D-Peru, is among the legislative participants.

The DPU hasn’t responded to either appeal. It also hasn’t responded to a petition by Attorney General Maura Healey to freeze the pipeline contract agreement cases until the broader issue of the region’s gas capacity needs is resolved in other pending cases before the commission. “In the meantime, the DPU has moved forward with an accelerated procedural schedule, foreclosing NEES from any participation whatsoever in the proceeding, causing irreparable harm to the rights of NEES and its members,” that group said in its petition to the court, citing the DPU’s “refusal” to render a final decision. Without a final decision from the Commission, NESS has been deprived of any participation in the hearing process.”

PLAN-NE has not yet filed a court appeal of its DPU rejection, but Wednesday filed motions urging the DPU to expedite a decision on its appeal and slow the process to allow time to prepare for next week’s hearings. It also filed motions to compel Berkshire Gas, Columbia Gas and National Grid (Boston Gas) to provide unredacted copies of all testimony, pleadings, responses and correspondence in the pipeline-related cases.

The DPU could make the NEES court action moot by denying the group’s appeal, although the June 11 court petition asks the court to halt the commission’s process so that it could then take its case directly to the full Supreme Judicial Court.

In DPU’s rejection of the two citizens’ full interventions — an action that was protested loudly throughout last week’s four-hour public hearing in Greenfield — it ruled that the DPU and the Department of Energy Resources adequately represent the interests of the groups and their members on rates and energy-efficient infrastructure.

NEES, through its founding members, represents more than 100,000 people, with more than 50,000 acres either owned or in conservation restriction in all of the towns served by Berkshire Gas.

“NEES is not seeking to intervene in this matter in order to disrupt the proceedings or to otherwise cause unnecessary delay,” writes the group’s attorney, Vincent DeVito, in the petition. “NEES represents a large collection of ratepayers, landowners, municipalities, and a legislator with unique interests in this matter and will be a sophisticated and responsible party with relevant insight.”

The group, he writes, was created last year to investigate and advocate on economic and environmental impacts of energy projects like the planned natural gas pipeline “specifically because of its position that government agencies were not sufficiently acting to carry out this important mission.”

At last week’s Greenfield public hearing, a representative of the attorney general’s office reiterated its call to freeze the DPU process on the pipeline contract cases.

At next week’s scheduled DPU evidentiary hearings, the attorney general’s office plans to conduct “a thorough cross-examination of the company’s witnesses,” according to office spokeswoman Chloe Gotsis.

You can reach Richie Davis at: rdavis@recorder.com or 413-772-0261, ext. 269